SC Lowy

Greenpark – London

Scope of Works:

  • Space Planning & Design Consultancy
  • Project Management
  • Glass Partitioning
  • Power and Data
  • Server Room
  • LED Lighting
  • Office Furniture
  • Flooring

Size:
2,000 sq/ft
Timescale:
3 weeks

SC Lowy, an international banking and finance group decided to open the first London office of their own, Divo Interiors were appointed to transform the space into a modern, bright, and functional office.

The key challenge was to refurbish the entire space whilst the offices remained occupied – this meant a phased weekend works to minimise downtime.

Everything from flooring, power, glazed partitioning to a complete new data infrastructure and new office furniture was installed in the fit-out process.

This fit-out was completed on time and within budget, despite the tight timescale of only 3 weeks.